Parliament Street Bridge Refurbishment, Nottingham
About the project
This Victorian bridge in central Nottingham once crossed the Great Central Railway outside Nottingham Victoria station. Since hidden from view due to the closure of the railway, comprehensive repairs were required to keep the bridge serviceable.
Key details
- Client
- Capital Shopping Centres (now Intu)
- Project manager
- Workman LLP
- Project value
- £1.1m
- Duration
- 35 weeks
Key aims and challenges
In the 1970s, the Victoria Centre shopping complex was opened on the site of the railway. Its basement car park now lies underneath the bridge.
The ingress of rain and salted water from winter gritting had severely corroded
and reduced the strength of the bridge.
We also upgraded the Victoria Centre's basement car park's M&E equipment, including lighting, emergency sprinkler system, roller shutter doors, and air conditioning.
How did we do?
The works were completed 4 weeks inside the programme period and for 15% less than the tendered allowance. Our Senior Agent was awarded the CECA Midlands Site Manager of the year for his management of the scheme.