| Scheme |
The construction of a roundabout on the A1307 Trunk Road between Cambridge and Colchester |
| Location |
Babraham Cambridgeshire |
| Date |
Start: August 2007 Finish: December 2007 |
| Contract Period |
18 weeks |
| Contract Value |
£1,100,000 |
| Project Manager |
George Smith Ernest Pasterfield Sevenoaks Kent |
| Adopting Engineer |
Michael Oakman Cambridgeshire County Council
| |
|
A roundabout was constructed on line and at grade on the trunk road to provide access to the Babraham Institute. The road was open throughout the whole of the construction period with the only restriction being a 50mph speed limit which was imposed for the safety of our workforce.
|